Meghalaya Tourism Development and Investment Promotion Scheme 2012 started on 20th Jan 2012 under the Tourism Department sponsored by the state to assist in the creation of tourism infrastructure in the form of homestays and resorts

Authority

State

Region

Meghalaya

Status

Verified 2026

Updated

March 2026

What you get

Who can apply

The cost of the project should be within Rs 16.00 Lakhs for homestays and within Rs 100.00 Lakhs for resorts. In case the project cost is above Rs 16.00 Lakhs for homestays and above Rs 100.00 Lakhs for resorts the assistance would be limited to 30% of the amount of Rs 16.00 Lakhs for homestays and 30% of the amount of Rs 100.00 Lakhs for resorts.; The entrepreneur should own the land for the project in the case of Resorts and should be the owner of the property with built-up houses in the case of homestays.; The project should be completed within a period of 18 (eighteen) months from the date of disbursement of the incentive for the Resort and within a period of 12(twelve) months in case of homestays.; The scheme is available only for units set up on or after the date of notification of the incentive scheme.; The entrepreneur will have to follow the Minimum Wage policy of the Government.

Required Paperwork

  • Aadhaar Card
  • PAN Card
  • Income Certificate
  • Residence Proof (Domicile)

Common Questions

In case of homestay what is the % contribution of the entrepreneur’s from the project cost?

2%

In case of resort what is the % contribution of the entrepreneur’s from the project cost?

2%

What is the cost of the project in case of Homestays?

Within Rs 16.00 Lakhs.

What is the cost of the project in case of Resorts?

Within 100 Lakhs.

What is the eligibility of the entrepreneur’s in case of Homestays?

The entrepreneur should be the owner of the property with built-up house.

What is the eligibility of the entrepreneur’s in case of Resort?

The entrepreneur should own the land for the project.

What is the duration to complete the project for Homestay?

The project should be completed within a period of 12 (twelve) months from the date of disbursement in case of homestay.

What is the duration to complete the project for Resorts?

The project should be completed within a period of 18 (eighteen) months from the date of disbursement in case of resort.

What is the cost of Application Form & Scheme Brochure?

Rs. 5000

Is the amount refundable?

No